Client:
|
Alcazar
|
|
EPC: TSK
|
Main Mechanical Contractors: OLP Tech |
|
Location:
|
Benban, Aswan, Egypt |
|
Project’s Duration: 9 months (From 08/06/2018 to 30/03/2019)
|
|
HSE: There are no casualties within the project.
|
|
Status: |
Completed and delivered. |
||
|
Scope of Work: Mechanical works including Soltec Trackers and PV Module installation. Engineers, technicians and supervisors of the project were supplied by Al-Rawan (30,600 Man days) |
|||||||
|
Client:
|
Access
|
|
EPC: TSK
|
Main Mechanical Contractors: Tek Solar - FGM |
|
Location:
|
Benban, Aswan, Egypt |
|
Project’s Duration: 6 months (From 09/10/2018 to 30/04/2019)
|
|
HSE: There are no casualties within the project.
|
|
Status: |
Completed and delivered. |
||
|
Scope of Work: Mechanical works including Soltec Trackers and PV Module installations. Engineers, technicians and supervisors of the project were supplied by Al-Rawan (19,150 Man days) |
|||||||
|
Client:
|
Scatec
|
|
EPC: Scatec
|
Main Mechanical Contractors: Sun Infinite – Green Cells JV |
|
Location:
|
Benban, Aswan, Egypt |
|
Project’s Duration: 6 months (From 01/02/2019 to 30/07/2019)
|
|
HSE: There are no casualties within the project.
|
|
Status: |
Completed and delivered. |
||
|
Scope of Work: Mechanical and Electrical works including PVH Trackers and Bifacial PV Module installations. Engineers, technicians and supervisors of the project were supplied by Al-Rawan (28,600 Man days) |
|||||||
|
Client:
|
Tawakol
|
|
EPC: Enneray
|
Main Mechanical Contractors: Sun Infinite – Green Cells JV |
|
Location:
|
Benban, Aswan, Egypt |
|
Project’s Duration: 3 months (From 15/03/2019 to 30/06/2019)
|
|
HSE: There are no casualties within the project.
|
|
Status: |
Completed and delivered. |
||
|
Scope of Work: Mechanical and Electrical works including PV Module installations. Engineers, technicians and supervisors of the project were supplied by Al-Rawan (8,900 Man days) |
|||||||
|
Client:
|
NREA
|
|
EPC: TSK
|
Main Mechanical Contractors: Tek Solar FGM |
|
Location: |
Fares, Aswan, Egypt |
|
Project’s Duration: 4 months (From 25/06/2019 to 28/10/2019)
|
|
HSE: There are no casualties within the project.
|
|
Status: |
Completed and delivered. |
||
|
Scope of Work: Mechanical works including Fixed Tables and PV Module installation. Engineers, technicians and supervisors of the project were supplied by Al-Rawan (7,600 Man days) |
|||||||
© Copyright 2019, All right reserved by AlRawan Solar